CASE STUDY / FOERMLI SYSTEM

CASE STUDY 02 | LIWAN COMMERCIAL PROJECT

Improving Structural Performance and Architectural Flexibility

Liwan Commercial Project
15%Less reinforcement
15%Lower slab weight
11 mMaximum Span

Project Overview

The Liwan Commercial Project compared Traditional Solid Slab and Foermli Voided Slab designs for a maximum span of 11 m, a live load of 5 kN/m² and a superimposed dead load of 4 kN/m².

Structural Design

Traditional system: 32 cm solid slab with a 20 cm drop beam below the slab (52 cm total depth).

Foermli system: 30 cm voided slab with an 18 cm drop panel below the slab (48 cm total depth).

Key Results

• 15% savings in slab reinforcement steel

• 15% reduction in slab weight

• 15% savings in execution time

• 15% savings in concrete weight in slabs

• 286 cm total building height savings (22 cm per floor × 13 floors)

Additional Benefits

The study identifies easier mechanical and electrical installations, better thermal and acoustic insulation, greater architectural flexibility, and smaller column sections due to reduced structural loads.

The project also achieved a reported height saving of 22 cm per floor, totaling 286 cm across 13 floors.

Conclusion

The Foermli Voided Slab design achieved savings in reinforcement steel, slab weight, concrete weight and execution time, while supporting improved architectural flexibility and MEP integration.